Water Crisis May Delay Hyd Projects, Push Home Prices Up by ₹200 per Sq Ft
Water shortage is putting Hyderabad’s residential construction sector under pressure, with 350–400 ongoing projects reportedly affected.
SAMUEL JOSHUA
Hyderabad: Water shortages are adding to construction expenses for residential projects across Hyderabad, with developers spending more on private tankers as borewell supplies dry up. The problem is particularly serious in the western corridor, where large gated communities require substantial quantities of water. Industry estimates suggest that 350 to 400 ongoing residential projects across the city are facing the impact of the shortage, raising concerns over construction costs and scheduled handovers.
The shortage has reached a point where water allocation and restrictions on consumption may become unavoidable. The government may have to introduce water rationing to curb excessive use and ensure adequate supplies for essential needs, said Prahalad, Director of Radhe Constructions and Consultants.
Private tanker water is reportedly costing around ₹3,000 per load, compared with nearly ₹1,000 for borewell water. According to industry estimates, the additional expenditure added around ₹10 per sq ft to construction costs. Developers are also considering whether the higher procurement costs will have to be reflected in property prices. Prahalad said the higher cost of arranging water could affect both construction budgets and project completion schedules, with developers facing the prospect of passing on part of the additional expenditure to homebuyers.
Depending on the project's size and location, the increase could be ₹100 to ₹200 per sq ft. He also warned that continued water shortages could delay construction by three to six months, pushing some projects scheduled for handover in 2027 into 2028. If the shortage becomes severe, developers may even have to consider temporarily halting construction until the water situation improves.
Related: El Nino: Hyderabad’s Construction Sector Stares at
Focus on Treated Wastewater Usage
Large residential communities in western Hyderabad are bearing the brunt of the water shortage because of their high daily requirements. Projects with 30 to 50 floors need substantial quantities of water for construction and residents' use, with some communities depending on 10 to 15 tankers a day.
Standalone residential buildings are also struggling to meet their water requirements as borewells fail to yield sufficient supplies.
In some locations, drilling to depths of around 200 feet has not yielded adequate groundwater, said Prahalad, leaving them dependent on private tankers. Buildings with five to seven floors are estimated to spend ₹25,000 to ₹30,000 a month on tanker supplies.
Despite the shortage, treated sewage water from sewage treatment plants (STPs) is not being fully utilised for construction and other purposes. Several gated communities have treated water that is being discharged into drains.
This water should be made available to builders for construction through proper coordination between the water board and housing associations, Prahalad added. The Hyderabad Metropolitan Water Supply and Sewerage Board's (HMWSSB) green tanker initiative supplies treated water for non-drinking purposes, including construction, curing, gardening and landscaping. However, a reliable distribution network is needed to make it a practical alternative for more projects.
Prahalad also called for stricter enforcement of restrictions on using potable water for construction, saying penalties would be necessary to ensure compliance. He said household water requirements must take priority if the shortage worsens and called on residents, developers, and housing associations to use water carefully, stressing that conservation is everyone's responsibility.