Sale Agreement Violations Land Aliens Developers ₹2-Crore Penalty
TG-RERA has imposed a ₹2-crore penalty on Aliens Developers for violating RERA provisions in its Aliens Space Station Township project at Tellapur.
PROPERTY PULSE
Hyderabad: A delayed home purchase has drawn a ₹2-crore penalty against Aliens Developers, after the Telangana Real Estate Regulatory Authority (TG-RERA) found that the company collected more than the permitted advance without a registered sale agreement and later offered terms that weakened buyers’ statutory protections.
In an order dated November 25, the Authority directed the developer to pay the penalty within 60 days over its Aliens Space Station Township project at Tellapur.
The case arose from a couple who booked a 1,412-sq-ft flat in Station 1 in October 2022. The buyers paid Rs 40.15 lakh towards the sale price and Rs 1.96 lakh for interior works, totalling ₹42.11 lakh. The developer acknowledged receiving the amount. However, the project was registered with TG-RERA only in November 2023, after the booking.
The Authority noted that sale-related payments amounted to about 38% of the flat’s cost, although Section 13(1) of the RERA Act bars a promoter from collecting more than 10% before executing and registering an agreement for sale. It also found that the draft agreement shared in September 2025 deviated from the format submitted at registration. The draft widened the force majeure clause, linked possession to payment of 50% of the cost followed by 19 months and a further 12-month grace period, and offered delay interest of ₹3 per sq ft per month.
The Authority said this was below the interest payable under state rules. The developer informed the Authority that construction had been delayed due to financial constraints and that completion was expected around April 2028. It also indicated that it would seek an extension. However, the Authority held that a proposed extension could not substitute for a definite possession date for buyers.
TG-RERA asked the developer to give the buyers the approved sale agreement within seven days. If the buyers decide to withdraw because the developer cannot give a clear possession date, the company must return the ₹42.11 lakh they paid, along with 10.85% annual interest from the dates of payment. The refund must be made within 60 days, with no cancellation charges deducted.
Also Read: Land Dispute Non-Disclosure Costs GKH Properties ₹6.10-Cr Penalty